98.07% 76.70% |
Percent of Phase 1 budget expended through end of Feb. 2013 Percent of Phase 2a budget expended through the end of Feb. 2013 |
35.9% 15.9% 2.8% 17.36% |
Overall construction participation by Small Business Enterprises Minority Business Enterprise participation Women Business Enterprise participation Combined Minority and Female workforce participation |
Construction: Bid Package #12-1 (Trade Contract 30) to be bid in March 2013.
Leasing: Residential is 100% leased; commercial space 94% leased.
416,307 1,786 |
Hours worked on site without a lost-time accident (through 12/31/11) Number of workers completing safety orientation |
Crews have logged 416,307 hours on site through December 2011 with no lost-time accidents. This is a major milestone for the Project team. Weekly site safety inspection evaluations assessing worker safety compliance are averaging 98%. The U.S. Department of Labor, Occupational Safety and Health Administration (OSHA), Messer Construction Co., the City of Cincinnati, and Hamilton County have developed a Health & Safety Partnership Agreement Plan. The Partnership’s common goal is to ensure a safe and healthy environment for individuals working on The Banks project through increased training, implementation of best work practices, enhanced safety and health programs, and compliance with applicable OSHA standards and regulations. OSHA has endorsed Messer Construction Co.’s nationally recognized “Safety4Site” commitment to safety training and accountability on The Banks construction project site.
- Cincinnati-based Prus Construction will begin more infrastructure improvements to #TheBanks –learn about the updates: t.co/H2nzUbY8Yl